Tokyo (AFP) June 17, 2014


This handout picture taken and released by Tokyo Electric Power Co. (TEPCO) on June 2, 2014 shows an excavator drilling in the ground at TEPCO's Fukushima Dai-ichi nuclear power plant at Okuma in Fukushima prefecture. TEPCO on June 2 started work on an underground ice wall at the crippled Fukushima nuclear plant, freezing the soil under broken reactors to slow the build-up of radioactive water. Image courtesy AFP.

The operator of Japan's battered Fukushima nuclear power plant said Tuesday it was having trouble with the early stages of an ice wall being built under broken reactors to contain radioactive water.

Tokyo Electric Power (TEPCO) has begun digging the trenches for a huge network of pipes pipes under the plant through which it intends to pass refrigerant.

This will freeze the soil and form a physical barrier that is intended to prevent clean groundwater flowing down mountainsides from mixing with contaminated water underneath the leaking reactors.

TEPCO said Tuesday a smaller, inner ice wall whose pipes it sank earlier to contain the already-contaminated water was proving difficult.

"We have yet to form the ice stopper because we can't make the temperature low enough to freeze water," a TEPCO spokesman said.

"We are behind schedule but have already taken additional measures, including putting in more pipes, so that we can remove contaminated water from the trench starting next month."

The coolant being used in the operation is an aqueous solution of calcium chloride, which is cooled to -30 degrees Celsius (-22 Fahrenheit).

The idea of freezing a section of the ground, which was proposed for Fukushima last year, has previously been used in the construction of tunnels near watercourses.

However, scientists point out that it has not been done on this scale before nor for the proposed length of time.

Coping with the huge -- and growing -- amount of water at the tsunami-damaged plant is proving to be one of the biggest challenges for TEPCO, as it tries to clean up the mess after the worst nuclear disaster in a generation, in which three reactors went into meltdown.

As well as all the water used to keep broken reactors cool, the utility must also deal with water that makes its way along subterranean watercourses from mountainsides to the sea.

Full decommissioning of the plant at Fukushima is expected to take several decades. An area around the plant remains out of bounds, and experts warn that some settlements may have to be abandoned because of high levels of radiation.

.


Related Links
Bringing Order To A World Of Disasters
A world of storm and tempest
When the Earth Quakes






Comment on this article via your Facebook, Yahoo, AOL, Hotmail login.

Share this article via these popular social media networks
del.icio.usdel.icio.us DiggDigg RedditReddit GoogleGoogle








DISASTER MANAGEMENT
Japan starts building underground ice wall at Fukushima
Tokyo (AFP) June 02, 2014
Japan on Monday started work on an underground ice wall at the crippled Fukushima nuclear plant, freezing the soil under broken reactors to slow the build-up of radioactive water, officials said. The wall is intended to block groundwater from nearby hillsides that has been flowing under the plant and mixing with polluted water already there. The Nuclear Regulation Authority, the national ... read more


DISASTER MANAGEMENT
Genome could unlock eucalyptus potential for paper, fuel and fiber

More than just food for koalas -- eucalyptus -- a global tree for fuel and fiber

EU agrees plan to cap use of food-based biofuels

York scientists provide new insights into biomass breakdown

DISASTER MANAGEMENT
Supercomputer emulates teenager to pass 'Turing Test'

Football-playing robots eye their own cup, and beyond

New computer program aims to teach itself everything about anything

DARPA Z-Man Program Demonstrates Human Climbing Like Geckos

DISASTER MANAGEMENT
Massachusetts to host sixth U.S. lease for offshore wind energy

London signs off on 240-turbine offshore wind farm

Scotland attracts more investments to renewable energy sector

Wind turbine payback as fast as 8 months

DISASTER MANAGEMENT
Global automakers split on 'green car' strategy

Tesla gives up patents to 'open source movement'

European taxis cause chaos in app protest

Elon Musk: 'We could definitely make a flying car'

DISASTER MANAGEMENT
Coal consumption highest since 1970

Charging Portable Electronics in 10 Minutes

Funky ferroelectric properties probed with X-rays

Magnetic cooling enables efficient, 'green' refrigeration

DISASTER MANAGEMENT
Japan minister apologises for Fukushima money gaffe

Nuclear waste dump plan on Aboriginal land abandoned

AREVA awarded a contract to provide services for Kozloduy 5 and 6 VVER nuclear reactors

AREVA to provide additional modernization services for Gosgen Facility in Switzerland

DISASTER MANAGEMENT
Japan plans carbon offset scheme with India: report

How Much Energy Will the 2014 World Cup Consume?

US invests in technology to make electric grid more secure

Report Estimates Costs and Benefits of Compliance with Renewable Portfolio Standards

DISASTER MANAGEMENT
Australian natural wonders under UNESCO spotlight

Saving trees in tropics could cut emissions by one-fifth

Forest loss starves fish

For forests, an earlier spring than ever




The content herein, unless otherwise known to be public domain, are Copyright 1995-2014 - Space Media Network. All websites are published in Australia and are solely subject to Australian law and governed by Fair Use principals for news reporting and research purposes. AFP, UPI and IANS news wire stories are copyright Agence France-Presse, United Press International and Indo-Asia News Service. ESA news reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. Advertising does not imply endorsement, agreement or approval of any opinions, statements or information provided by Space Media Network on any Web page published or hosted by Space Media Network. Privacy Statement All images and articles appearing on Space Media Network have been edited or digitally altered in some way. Any requests to remove copyright material will be acted upon in a timely and appropriate manner. Any attempt to extort money from Space Media Network will be ignored and reported to Australian Law Enforcement Agencies as a potential case of financial fraud involving the use of a telephonic carriage device or postal service.